The WANDRRA works programme continues, the following roads are complete and ready for inspection:

Billericay East Road SLK 0.00 to 28.60 except culverts require cleanout SLK 13.05, 15.88, 22.19, 23.20 and 27.86
Billericay West Road SLK 10.36 to 12.44
Brown Road SLK 0.28 to 12.35
Cheethams Road SLK 0.00 to 7.53
Hedges West Road SLK 0.00 to 11.96
Koolberrin Road SLK 0.00 to 7.92
Malones Road SLK 0.00 to 2.60 (note there is no SLK 3.00 to 4.13 or 4.85 to 6.46 or 7.60 to 8.30)
Narembeen Boundary Road SLK 0.00 to 6.38
Narembeen South Road SLK 14.77 to 23.48

Works program up until December 19th 2017:

Construction grading Hedges East Road SLK 0.30 to 5.82 ready for re-sheeting
Re-sheeting Cumminin Road SLK 4.22 to 5.10 from 29/11/2017 to 30/11/2017
Re-sheeting Cumminin Road SLK 5.50 to 6.67 from 5/12/2017 to 7/12/2017
Re-sheeting Hedges East Road SLK 0.30 to 5.82 from 8/12/2017 to 19/12/2017

Works program for January 2018 includes:-

Emu Hill East Road SLK 0.89 to 4.55 – Heavy Construction Grade
Erdman Road SLK 0.00 to 8.56 – Construction Grade and re-sheeting where stipulated